Process ID ACQ.14
Process Name Request for proposals ACQ.14 Request for proposals Process Purpose The purpose of the Request for proposals process is to prepare and
issue the necessary acquisition requirements. The documentation will
include, but not be limited to, the contract, project, finance and
technical requirements to be provided for use in the Call For Proposals
(CFP)/Invitation To Tender (ITT).
Process Outcomes As a result of successful implementation of this process:
1) rules are defined for proposal/tender invitation and evaluation which
comply with the acquisition policy and strategy;
2) the baseline technical and non-technical requirements are
assembled to accompany the CFP/ITT;
3) the agreement (contractual) terms of reference and conditions for
CFP/ITT are established;
4) the financial terms of reference for costs and payments for CFP/ITT
are defined;
5) the project terms of reference for CFP/ITT are defined;
6) the technical terms of reference for CFP/ITT are defined; and
7) a CFP/ITT is prepared and issued in accordance with acquisition
policies and which complies with relevant national, international and
regulatory laws, requirements, and policies.
3.1.7
Process ID ACQ.15
Process Name Supplier qualification
Process Purpose The purpose of the Supplier qualification process is to evaluate and
determine if the potential supplier(s) have the required qualification for
entering the proposal/tender evaluation process. In this process, the
technical background, quality system, servicing, user support
capabilities and etc. will be evaluated.
Process Outcomes As a result of successful implementation of this process:
1) criteria are established for qualifying suppliers;
2) supplier capability determination is performed as necessary;
3) the suppliers which possess required qualification are short-listed
for tender solution(s) evaluation;
4) any shortfalls in capability are identified and evaluated; and
5) any corrective action required by the acquirer is evaluated and
performed. ACQ.15 Supplier qualification