spice规范V4.5

3.1.5

Process ID ACQ.13

Process Name Project requirements

Process Purpose The purpose of the Project requirements process is to specify the

requirements to ensure the acquisition project is performed with

adequate planning, staffing, directing, organizing and control over

project tasks and activities. ACQ.13 Project requirements Process Outcomes As a result of successful implementation of this process:

1) consistency between financial, technical, contract and project

requirements is established;

2) requirements for the organisational, management, controlling, and

reporting aspects of a project are defined;

3) requirements for adequate staffing of projects by a competent team

(e.g. legal, contractual, technical, project competent resources) with

clear responsibilities and goals are defined;

4) the needs for exchanging information between all affected parties

are established;

5) requirements for the completion and acceptance of interim work

products and release of payments are established;

6) potential risks are identified;

7) requirements for ownership of interactions and relationships with

suppliers are defined;

8) rights for use and distribution of the product by the customer and

supplier are defined; and

9) support and maintenance requirements are established.

automotiveSIG_PRM_v45(19).doc 将本文的Word文档下载到电脑