Design and Evaluation of Tailings Dams

Figure 4. Single (a) and Multiple (b) Side-Hill Impoundments

(Source: Vick 1990)

Other types of valley impoundments may be employed when there is an excessively large drainage catchment

area and/or there is a lack of necessary valley topography. Two variations are the side-hill impoundment and

the valley-bottom impoundment. The side-hill layout consists of a three-sided dam constructed against a

hillside (Figure 4). This design is optimal for slopes of less than 10% grade. Construction on steeper slopes

requires much more fill volume to achieve sufficient storage volume (especially when using the downstream

method of construction).

If the drainage catchment area is too large for a cross-valley dam and the slope of the terrain is too steep for a

side-hill layout, then a combination of these two designs, the valley-bottom impoundment, may be considered

(Figure 5). Valley-bottom impoundments are often laid out in multiple form as the valley floor rises, in order

to achieve greater storage volume. Because the upstream catchment area is relatively large, it is often, or

usually, necessary to convey upstream flows around (and/or under) valley-bottom impoundments.

The valley dam configurations are often the optimum choice for economic reasons. This is because the valley

walls form one or more sides, so that the dam length is reduced, minimizing construction costs. However,

decreased construction costs and low average depth of tailings in the embankment may be offset by increased

environmental mitigation and increased costs of shut-down and reclamation.

技术报告-尾矿库设计及评估 (英文)(14).doc 将本文的Word文档下载到电脑

精彩图片

热门精选

大家正在看

× 游客快捷下载通道(下载后可以自由复制和排版)

限时特价:7 元/份 原价:20元

支付方式:

开通VIP包月会员 特价:29元/月

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信:fanwen365 QQ:370150219