技术报告-尾矿库设计及评估 (英文)(10)
时间:2025-02-22
时间:2025-02-22
技术报告-尾矿库设计及评估 (英文)
Design and Evaluation of Tailings Dams
Retention dams are constructed at full height at the beginning of the disposal whereas raised embankments
are constructed in phases as the need for additional disposal capacity arises. Raised embankments begin with
a starter dike with more height added to the embankment as the volume of tailings increases in the
impoundment.
Tailings retention dams (Figure 1) are similar to water retention dams in regard to soil properties, surface
water and ground water controls, and stability considerations. They are suitable for any type of tailings and
deposition method.
Figure 1. Water-Retention Type Dam for Tailings Disposal
(Source: Vick 1990)
Raised embankments can be constructed using upstream, downstream, or centerline methods, which are
explained in more detail in a later section (see Figure 2). Each of the structures in Figure 2, for instance, is
constructed in four successive lifts, with constructing material and fill capacity increasing incrementally with
each successive lift. They have a lower initial capital cost than retention dams because fill material and
placement costs are phased over the life of the impoundment. The choices available for construction material
are increased because of the smaller quantities needed at any one time. For example, retention dams generally
use natural soil whereas raised embankments can use natural soil, tailings, and waste rock in any
combination. (Vick 1990)
下一篇:基坑土方开挖方案