湿地路基施工方案-CH(8)

时间:2025-04-22

南方湿地施工的一些施工方案

SHANDONG LUQIAO GROUP CO., LTD PACKAGE EX-8 FROM KM81+300.00 TO KM96+300.00 HA NOI- HAI PHONG EXPRESSWAY PROJECT ———— ———— Km10,Pham Van Dong Str., Duong Kien Dist.,Haiphong City Tel: +84-313581562 Fax: +84-313581565

Method Statement for Embankment Construction SDLQ-MS-SDC-A2-EN

SITE ORGANISATION

Project Manager Wang yu chi

Q.C Manager/ Chief Engineer Liu xiang Diao peng dong Cao kai xuan Guo zen fu Site Manager Admin. Manager Financial Manager

TrafficLaborator y Survey and Design Team Quality control Dept. Contract manag. and Payment Gong yun juan Xu fu sheng Wu feng Diao peng Dept. Liu xiang dong Yi shao liang Hu chun guang 工程生产 Dep.t Equi. & Material Dept. SafetyEnvironme ntal Control Dept. Cao kai xuan Guo zen fu Admin. Dept. Accounting and Finanancia l Dept.

Revision A1,

February 10, 2009

-Page 8 of 17

南方湿地施工的一些施工方案

施工主要机械设备表

备注:表中各种机械的数量会根据现场实际情况增减以满足实际要求。

2.4 材料要求 2.4.1 路基填料

路基填料所用黑砂为业主供应,我项目部会与工程师联合取样送检,确保达到相关检测标准和规范要求。我部将严格控制进场材料的质量,若含草皮土、生活垃圾、树根及腐朽物质的材料严禁进场。

用于路堤施工的材料应符合下列要求:

湿地路基施工方案-CH(8).doc 将本文的Word文档下载到电脑

精彩图片

热门精选

大家正在看

× 游客快捷下载通道(下载后可以自由复制和排版)

限时特价:7 元/份 原价:20元

支付方式:

开通VIP包月会员 特价:29元/月

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信:fanwen365 QQ:370150219