BDDQ-ZW-16接地系统安装作业指导书傍浦
时间:2025-04-20
时间:2025-04-20
220kV傍浦变电站工程 接地系统安装作业指导书
编码:BDDQ-ZW-16
广西送变电建设公司 220kV傍浦变电站工程项目部
二〇一二 年 七 月
作业指导书签名页
目 次
1 适应范围··································································4 2 编写依据··································································4 3 作业流程··································································4 4 安全风险辨析与预控························································4 5 作业准备··································································5 6 作业方法··································································6 7 质量控制措施及检验标准···················································15
1 适用范围
1、 本工程新建220kV傍浦变电站工程项目,本期接地系统均采用约1.1万米热镀锌扁钢作为全站地网接地,装设独立避雷针等方式作为本站接地系统。 2、作业地点:220kV傍浦变电站全站配电区。
3、本工程项目运行单位为钦州供电局,建设单位为广西电网公司建设分公司,设计单位为广西博阳电力设计有限责任公司了梧州分公司,监理单位为广西正远电力工程建设监理有限责任公司。
4、本作业指导书适用于变电站内主接地网、构筑物避雷、二次接地网等接地系统安装作业。 2 编写依据
表2-1 编 写 依 据
3 作业流程
作业(工序)流程见图3-1。
图3-1 作业(工序)流程图
4 安全风险辨析与预控
4.1接地系统安装作业前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。 4.2 按《指南》中与接地系统安装作业相关联的《电网建设安全施工作业票》(编码:BDDQ-ZW-16-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施工负责人签发。
4.3 施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人员负责将安全措施落实到各作业任务和步骤中。
4.4 安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须重新办理作业票,在工作完成后上交项目部保存备查。
220kV傍浦变接地系统安装作业
5 作业准备 5.1 人员配备
表5-1 作业人员配备表
5.2 主要工器具及仪器仪表配置
表5-2 主要工器具及仪器仪表配置表
6 作业方法
6.1主接地网安装
6.1.1根据接地装置平面布置图标高及平面尺寸用白石灰粉测量放样,在土建路基、排水、基础开挖同步进行。
6.1.2接地网地沟的开挖采用挖掘机和人工相结合的开挖方式,在施工场地开阔,与土建工程施工不会出现交叉的地方用挖掘机进行开挖;在土建已施工,局部无法用挖掘机开挖的地方,采用人工进行作业。
6.1.3水平接地带采用镀锌圆钢敷设,站内水平接地网的埋设深度为相对0m以下0.8m,最外缘角水平接地带要求圆弧半径不小于6 m。焊接接地圆钢时搭接面双面焊,长度不小于6D(如图6-1),焊接完成后清除干净焊渣,然后涂上防锈红丹漆二道和防腐沥青漆一道。 6.1.4垂直接地极按图纸位置布置垂直打入地下 …… 此处隐藏:8318字,全部文档内容请下载后查看。喜欢就下载吧 ……
上一篇:足球队赞助合同书(修正版)
下一篇:自觉参与政治生活