1) INTRODUCTION

This guideline is prepared in view of the requirements for switchyard service inspection (visual) and condition based maintenance of substation equipments, structures and other miscellaneous items in substations. These guidelines are necessarily general. It is recommended to carry out maintenance of equipment as per manual supplied by manufacturer. All inspections and test procedures should also be performed in accordance with applicable codes and standards.

The aim of this guideline is to provide in general visual inspection check points for the structures, grounding systems, LT switchboards, etc. for which as such there is no readymade guidelines available. Also to provide the visual inspection and condition based maintenance of Major equipments like Transformer, Circuit breakers, CTs, CVTs, PTs, Disconnectors and LAs etc. to verify the health of the equipments.

Service visual inspection is the necessary activity to identify any visible abnormality or failure and require to be performed at specified interval. Whereas condition based monitoring checks (on line/ off line) are necessary to identify internal defects or abnormality, so that necessary preventive action can be taken up.

2) SERVICE INSPECTION & CONDITION MONITORING GUIDELINE

The substation in total and the individual items of equipment contained therein should be periodically inspected. Binoculars should be used to view buses and other equipment located on structures.

ABB-Substation-Condition-Monitoring-Schedule(2).doc 将本文的Word文档下载到电脑

精彩图片

热门精选

大家正在看

× 游客快捷下载通道(下载后可以自由复制和排版)

限时特价:7 元/份 原价:20元

支付方式:

开通VIP包月会员 特价:29元/月

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信:fanwen365 QQ:370150219