首件钻孔灌注桩施工工艺总结及作业指导
时间:2026-01-16
时间:2026-01-16
通过专家评审
目 录
1首件钻孔灌注桩工程施工概述 .......................................................................................... 1 2 详细施工工艺及图表 ......................................................................................................... 1
2.1 首件桩施工主要设备及用途 .................................................................................... 1 2.2 钻孔灌注桩施工工艺流程 ........................................................................................ 2 2.3 桩位放样 .................................................................................................................... 3 2.4钢护筒施工 ................................................................................................................. 4
2.4.1钢护筒的加工 .................................................................................................... 4 2.4.2钢护筒的吊运与堆放 ........................................................................................ 5 2.4.3钢护筒的插打 .................................................................................................... 5 2.5 钻孔平台搭设 ............................................................................................................ 6 2.6 钻孔泥浆 .................................................................................................................... 6
2.6.1 泥浆循环系统设置 ........................................................................................... 6 2.6.2泥浆的制备 ........................................................................................................ 7 2.7 钻机就位 .................................................................................................................... 9 2.8 成孔钻进 .................................................................................................................... 9 2.9 清孔 .......................................................................................................................... 10 2.10钢筋笼制作安装 ..................................................................................................... 10
2.10.1钢筋骨架的制作 ............................................................................................ 10 2.10.2钢筋骨架的吊装、运输与下放 .................................................................... 11 2.10.3钢筋笼安装中应注意的问题 ........................................................................ 12 2.11钻孔桩砼的灌注 ..................................................................................................... 13
2.11.1 混凝土的供应 ............................................................................................... 13 2.11.2 混凝土的浇筑 ............................................................................................... 13 2.11基桩检测 ................................................................................................................. 15 3首建钻孔灌注桩施工可能发生的风险及其对策 ............................................................ 15
3.1防坍孔对策 ............................................................................................................... 16 3.2防掉钻头、偏斜孔对策 ........................................................................................... 16
通过专家评审
3.3防断桩对策 ............................................................................................................... 16
通过专家评审
首件钻孔灌注桩施工工艺总结及作业指导
2004年5月28日,在我局领导和业主、监理的关心和指导下, 我部首件钻孔灌注桩胜利开钻了。我部通过对首件桩的成孔钻进、清孔、钢筋笼下放、安装导管、二清、砼浇筑等各个环节的全程记录,掌握了大量第一手资料,在成孔钻进和清孔过程中遇到了一些钻进前未预料到的问题,现对先前的施工工艺进行总结和改进,为以后的基桩全面开钻作最充分的准备。
1首件钻孔灌注桩工程施工概述
首件钻孔灌注桩我部选择91号墩右幅1号桩,其桩径为1.5m,桩长75.7m,混凝土设计方量为133.8m3。我部首件钻孔灌注桩拟采用KP2000型钻机先正循环造浆钻进、后反循环成孔钻钻进的方法钻进。根据现场记录显示,钻机自上而下穿过淤泥质亚粘土层(厚约25m)、亚砂土层(厚约8m)、亚砂土夹粉砂层(含少量砾石,厚约12m)、中粗砂层(厚34m以上),钻孔总共用了56小时。由于出现了一些钻孔前未预料到的情况,清孔泥浆中含砂率过高,用了约73小时清孔使泥浆达到了规范要求,后面将作重点分析。首件桩钢筋笼在钢筋预制场集中加工制造,用 50T履带吊将钢筋笼吊至孔位处并分节下放,钢筋笼下放分8节,用了约8个小时。钢筋笼下放完毕后进行砼导管安装和二次清孔,共用了约2小时。砼浇筑前进行了各项泥浆指标和桩底沉淀的检验,符合规范要求后进行砼浇筑,混凝土采用商品混凝土,浇筑时间用了3小时。
2 详细施工工艺过程及图表 2.1 首件桩施工主要设备及用途
见表2.1-1
首件桩施工主要设备及用途 表2.1-1
通过专家评审
2.2 钻孔灌注桩施工工艺流程
钻孔灌注桩施工工艺流程图见图2.2-1
通过专家评审
图2.2-1 钻孔灌注桩施工工艺流程图
2.3 桩位放样
我部已对业主提供的测量控制网进行了复测。对于首件桩91号墩1号桩,我部采用位于大 …… 此处隐藏:9198字,全部文档内容请下载后查看。喜欢就下载吧 ……